A Smooth Carve-Out: What Needs to Work in IT Starting the First Day After Closing

When a corporation sells a business unit, there are intense negotiations over the purchase price, employees, and customers. IT often doesn’t come up until late in the process—yet in many carve-outs, it’s the critical path. This is because the spun-off division typically uses the parent company’s systems, networks, licenses, and data centers. But the day after closing, that division belongs to someone else. How IT continues to operate will determine whether the new owner starts with a functioning business or a construction site.

The TSB Case: When the Spin-Off Turns into a Crisis

The British bank TSB illustrates just how high the risks can be. TSB was spun off from the Lloyds Banking Group, went public in 2014, and was acquired by the Spanish bank Sabadell in 2015 (Sky News). In April 2018, approximately 1.3 billion customer records were to be transferred from the Lloyds platform to a new system under Sabadell’s management (BBC).

Although the data was successfully migrated, the platform immediately experienced technical glitches. Branches, telephone, online, and mobile banking were affected, as was a significant portion of the 5.2 million customers. It took until December 2018 for operations to return to normal (FCA). TSB estimated the costs at 330 million pounds, and approximately 80,000 customers switched banks (BBC). In 2022, the British regulatory authorities imposed additional fines totaling 48.65 million pounds. They found that TSB had not adequately organized and managed the migration and had failed to control the risks associated with outsourcing to a critical IT service provider (FCA). An independent investigation concluded that more than 1,400 people and 70 vendors were involved and that robust testing was lacking (ITPro).

The lesson for every carve-out: The biggest risk isn’t the data transfer itself, but rather management, testing, and dependence on service providers.

Day 1 is not the end, but the beginning

In a carve-out, there are two crucial milestones. Day 1 is the first day after closing. Business must continue without interruption: employees can log in, invoices are issued, wages are paid, and customers are supplied. Exit is the moment when the spun-off company is fully operational on its own systems and no longer relies on services from the seller.

In between, there are usually transitional agreements, known as Transitional Service Agreements (TSAs). Under these agreements, the seller continues to operate the IT infrastructure for a limited time in exchange for payment. This sounds pragmatic, but it carries its own risks.

Five Questions That Must Be Answered Before Signing

1. What exactly is being spun off? A complete list of the applications, data, infrastructure, and contracts used by the spun-off division—including “invisible” corporate services such as identity management, networking, security monitoring, or printing services.

2. What must be functional on Day 1? Not everything needs to be separated immediately. The key is to determine which processes are business-critical and how they will operate on the first day—either independently or via TSAs.

3. How long will the TSAs run, and at what cost? TSAs are not part of the seller’s core business. Terms, service levels, prices, and renewal options must be clearly defined; otherwise, a costly dependency will arise.

4. What happens to licenses? Many software contracts permit use only within the corporate group. Upon closing, the spun-off division may suddenly find itself in a sublicensed status. Renegotiating with vendors takes time.

5. What is the target architecture? Will the company be integrated into a buyer’s platform, established as an independent entity, or migrated to modern cloud solutions? This decision determines the costs, duration, and risk of the entire program.

Typical Pitfalls in Transition Agreements

TSAs are unavoidable in almost every carve-out, but they are often negotiated under time pressure in the final weeks before signing. This leads to recurring problems.

Incomplete service descriptions. Anything not specified in the TSA will not be provided after closing—or only at an additional cost. Cross-functional services such as security monitoring, certificate management, or the maintenance of interfaces with customers and suppliers are particularly often omitted.

Lack of incentives for the seller. For the seller, the TSA is an obligation, not a business opportunity. The buyer’s requests for changes are given low priority, and specialized staff are pulled away as soon as the seller’s own organization needs them. Clear service levels, escalation procedures, and a joint steering committee are therefore essential.

Overly optimistic terms. Those who set the TSA term too short will run out of time and have to extend it at great expense. Those who set it too long remain dependent for an unnecessarily long time. Realistic planning is based on a robust separation plan—not on a figure agreed upon during negotiations.

Overlooked reversal procedures. At the end of the TSA, data must be returned or deleted, access revoked, and contracts terminated. This exit must also be prepared for both contractually and technically.

Typical Scenario: The Business Unit with the Shared SAP Instance

An industrial conglomerate sells a business unit with 1,200 employees to a financial investor. The business unit operates on the same SAP instance as the rest of the conglomerate, within shared company codes and using shared master data. A simple “copy” is not possible for data protection and competition law reasons, as the buyer is not permitted to receive any group data.

The solution is implemented in several steps: Until Day 1, the seller continues to operate the system under a TSA, with access technically restricted to the division’s data. At the same time, a cleaned-up, standalone copy of the system is set up, containing only the division’s data. After several test migrations and a dress rehearsal, the migration takes place over a long weekend. The TSA ends after 14 months—two months before the contractually stipulated latest deadline.

The key to success was not the technology, but the preparation: an early assessment of the current state, realistic TSA durations, clearly defined acceptance criteria, and a testing plan that simulates the actual migration scenario.

Conclusion

A carve-out is one of the most challenging IT projects imaginable: It must be carried out under time pressure, with limited access to information, and in coordination with a seller who has their own interests. Involving IT early in transaction planning can help avoid Day 1 risks, keep TSAs short, and lay the foundation for a modern, independent IT infrastructure. Twinlake supports carve-outs from separation planning through TSA design to migration and—upon request—into ongoing operations.

Dr. Karl Michael Popp is an M&A expert and author specializing in software company acquisitions.Contact: +49 6202 5829917 | www.drkarlpopp.com

Parts of this blog might be AI generated

Advertising section

A Modern Post-Merger Integration Playbook: From M&A Models to AI Solutions
By Dr. Karl Michael Popp

Master integration due diligence to transform your M&A success. Learn more at manda-automation.com

Previous
Previous

IT Due Diligence Isn’t Just a Box to Check on a Checklist: How Buyers Can Identify Hidden IT Risks Before Signing

Next
Next

IT Determines the Success of Integration: Why Synergies Are Often Lost in the System Landscape